Commissioners approve Andover sewer project

By CARL E. FEATHER - cfeather@starbeacon.com
Staff Writer

JEFFERSON — A scope of agreement for a sewer project on South Main in Andover Village received commissioners’ approval on Tuesday.

The funding is coming from the county’s 2011 Community Development Block Grant allocation. Cost of the entire project is estimated at $116,000. The block grant’s share is $45,700, with the Ohio Public Works Commission providing the balance.

The work involves 186 feet of new storm sewer line. The project must be substantially complete by May 31 and ready for payment within 30 days thereafter. Andover Village and United Survey Inc., of Oakwood Village, are the parties in the agreement.

In other action during the Tuesday agenda meeting, commissioners Daniel Claypool and Peggy Carlo approved: